first cog
first cog
second cog
third cog
fourth cog
fifth cog
sixth cog
small transparent gif for site construction purposes

crosscross

Bristol Gatelines

To provide the civil and building design associated with installing two new gatelines and reopening two public entrances.

ex
Scope of Works

To provide the civil and building design associated with installing two new gatelines and reopening two public entrances. Details included:

- Foundation for equipment (CIS, air conditioning and gateline equipment)
- Steelwork design for gate alterations, new barrier gates and emergency signs
- Building repairs to public areas
- Paving and drainage
- Roadway and traffic calming
- Cycle storage
- Signage and wayfinding

Deliverables

- Form 001, 002 and 003 under NR/L2/CIV/003
- Drawings
- Calculations
- Design decision log
- Designer's risk assessment

Key Achievements

- Accommodation of change and variance once construction started on site
- Good team communication to aid information flow

 

crosscross

Inverness Wheel Lathe

To provide design services for to support the new Mobiturn wheel lathe.

ex
Scope of Works

To provide design services for to support the new Mobiturn wheel lathe.

The existing jacking strips in the heavy maintenance shed do not extent far enough to allow a two-car lift. To avoid splitting units to use the Mobiturn, the jacking strips need to be extended.

Condition of existing slab and the capacity of the jacking strips is unknown so detailed structural investigations needed to be undertaken.

Deliverables

- Site topographical survey, ground investigation and structural coring
- Options study, outline and detailed design
- Drawings, specifications and calculations
- Designer's risk assessment
- Approved for Construction drawings
- As-built records and drawings

Key Achievements

- Early deployment to site for surveys, ground investigation and structural coring
- In-house survey management to give and early start on design activity
- Close liaison with construction team to achieve the tight programme for commissioning
- Developing good relationships and lines of communication early in the project through site visits, design review meeting and project meetings

 

crosscross

Bristol 11kV Diversion

Civils design submission for the installation of a new substation and associated cable routes at Bristol East Junction.

ex
Scope of Works

Civils design submission for the installation of a new substation and associated cable routes at Bristol East Junction. Design of new substation foundations and 11kV cable route to integrate with future proposed works for track, OLE and driver walking route.

Deliverables

- Cable route options report
- Detailed design submission drawings
- Submission of 3D model files
- Specifications and calculations
- Designers risk assessment
- Design decision log
- Form 001, 002 and 003 submission package and AFCs
- As-built drawings
- Form 001, 002 and 003 submission package for temporary works lift
- Form 002 and 003 submission for integration of substation GRP housing

Key Achievements

We were able to react quickly to provide site support during the construction phase to deal with emerging changes.

 

 

crosscross

Perth Temporary Service Provisions

Production of a track design submission and production of a civils design submission to accommodate and serve the new HST fleet to be serviced for fuel, CET, tanking/potable water and shore supplies.

ex
Scope of Works

To undertake a topographical and drainage survey on the servicing depot at Perth.

Production of a track design submission to accommodate the new HST fleet to be serviced.

Production of a civils design submission to serve the new fleet to be serviced for fuel, CET, tanking/potable water and shore supplies.

Deliverables

- Site topographical survey and drawings
- Detailed design submission drawings – track and civils
- Specifications and calculations – track and civils
- Design decision log – track and civils
- Designers risk assessment – track and civils
- Civils Form 002 and Form 003 submission package and AFCs
- Track Form A/B submission package and AFCs

Key Achievements

- Through our design development we achieved a more efficient catchment area for the on-site buried interceptor which in turn reduced the size of the interceptor and ultimately the cost of it.
- Effective GI and track design justifications resulted in cost savings by means of more efficient track specification (reduced the depth of the dig) and provision of serviceable materials.

 

 

crosscross

Moss Park PSP

To undertake a topographical survey of the proposed site for a new principal supply point (PSP) nearby Mosspark platform.

ex
Scope of Works

To undertake a topographical survey of the proposed site for a new principal supply point (PSP) nearby Mosspark platform.

Production of a civils design submission for the provision of a new PSP compound and equipment foundations within.

Deliverables

- Site topographical survey
- Options, outline and detailed design
- Drawings, specifications and calculations
- Design decision log
- Designers risk assessment
- Form 001, 002 and 003 submission package and AFCs
- As-built records and drawings

 

 

crosscross

Millburn Yard Servicing

The civils design of new servicing facilities for the Caledonian Sleeper train, from survey works investigating on-site services through to detailed design.

ex
Scope of Works

The civils design of new servicing facilities for the Caledonian Sleeper train, from early survey works, through options development, single option development and detailed design.  Servicing included shore supplies, access for cleaning and CET cycling. Items of civils design included earthworks and retaining walls to manage the existing ground levels, accommodation building, stores building, pump house, HV substation & switchgear, and shore supplies.  Track condition was also reviewed for continued use with gauge clearance checks undertaken.                                 

Deliverables

- Initial site survey
- Options Report
- Survey specification, Topographical survey and Ground Investigation
- Form 001 and Form 2 Package;

  • Designers Risk Assessment
  • Design Decision Log
  • Outline Drawings

- Form 003 Package

  • Designers Risk Assessment
  • Design Decision Log
  • Detailed Drawings
  • Calculations Pack

- Track Condition Report
- Inclusion of the Architectural and modular building supplier drawings into the civils submissions.

Key Achievements

The use of recessed-lid trough units within the walkway allowed for service routing local to CET points and walkway lighting whilst maintaining a flush finish across the walkway for trolleys.

Key Challenges

Determining route of services in restricted areas due to retaining structures, this was undertaken by good interaction with the M&E designer to minimise runs and group services where possible.

Placement of structures to provide good use of space whilst maintain existing road access. This was done by careful use of gradients and falls to allocate sufficient space for vehicle movements and working with the client team to understand future depot use and constraints.

Routing the proposed services through the new walkway apron presented a difficulty in a consistent slip-resistant surface across the walkway. This was designed using a pre-cast concrete trough unit with recessed lid, this allowed for a concrete lid for consistent slip resistance throughout the apron.

crosscross

Blackford

The design of civil elements to support the installation of a signalling power supply.

ex
Scope of Works

The design of civil elements to support the installation of a signalling power supply. Design details of compact PSP, distribution cabinet and lighting column foundations in addition to a generator laydown area were required to complete the design.

Deliverables

- Detailed design drawing of civil elements for inclusion in the electrical Form A/B submission
- Attendance at the IDC
- Issue of final AFC drawings

Key Achievements

Effective sharing of design data into ProjectWise collaborative model with drawings in MicroStation.

small transparent gif for site construction purposes